Achieved Milestones
Below you find the full progress of Cathy Hammer Secondary School, from the beginning of the facility construction in March 2021 until today:
SCHOOL OPENING
January 2023:
- the first 12 students of Form 1 started their classes on 9th of January 2023
MORE IMPRESSIONS HERE
INTERVIEWS & REGISTRATION
October 2022:
- interviews and employment of the teachers and other staff
- registration process for the first students
MORE IMPRESSIONS HERE
CONSTRUCTION
TOILET BLOCKS
August 2023:
- 1st of Aug. '23:
Completion of construction of toilet blocks for girls and boys
MORE IMPRESSIONS HERE
CONSTRUCTION
CLASSROOM BUILDING
October 2022 - August 2023:
- 15th of Oct. '22:
foundation - 14th of Nov. '22 - 3rd of March '23.:
groundfloor - 2nd floor - 4th of March '23 - now
Roofing & facade
MORE IMPRESSIONS HERE
FINISHING
LABORATORY BUILDING
August 2021 – June 2022:
- 2nd of Aug.:
foundation and blessing - 4th of Feb.:
roofing - 6th of June:
end of laboratory construction
MORE IMPRESSIONS HERE
SITE PREPARATION
March 2021 – July 2021:
- 13th of March - 7th of May:
timber preparation - 8th of May - 3rd of June:
cleaning and ground levelling - 1st of July - 30th of July:
site preparation