Achieved Milestones

Below you find the full progress of Cathy Hammer Secondary School, from the beginning of the facility construction in March 2021 until today:

SCHOOL OPENING
January 2023:

  • the first 12 students of Form 1 started their classes on 9th of January 2023


MORE IMPRESSIONS HERE

INTERVIEWS & REGISTRATION
October 2022:

  • interviews and employment of the teachers and other staff
  • registration process for the first students

MORE IMPRESSIONS HERE

CONSTRUCTION
TOILET BLOCKS
August 2023:

  • 1st of Aug. '23:
    Completion of construction of toilet blocks for girls and boys



MORE IMPRESSIONS HERE

CONSTRUCTION
CLASSROOM BUILDING
October 2022 - August 2023:

  • 15th of Oct. '22:
    foundation
  • 14th of Nov. '22 - 3rd of March '23.:
    groundfloor - 2nd floor
  • 4th of March '23 - now
    Roofing & facade 

MORE IMPRESSIONS HERE

FINISHING
LABORATORY BUILDING
August 2021 – June 2022:

  • 2nd of Aug.:
    foundation and blessing
  • 4th of Feb.:
    roofing
  • 6th of June:
    end of laboratory construction

MORE IMPRESSIONS HERE

SITE PREPARATION
March 2021 – July 2021:

  • 13th of March - 7th of May
    timber preparation
  • 8th of May - 3rd of June
    cleaning and ground levelling
  • 1st of July - 30th of July:
    site preparation

MORE IMPRESSIONS HERE