August 2021 - June 2022:
Laboratory block construction
1/24
02.08.2021 - Blessing by Fr. Firmati Tarimo & ground breaking
2/24
06.08.2021 - Excavation work & foundation preparation
3/24
17.08.2021 - Excavation work & foundation preparation
4/24
22.08.2021 - Foundation preparation
5/24
26.08.2021 - Foundation
6/24
31.08.2021 - Foundation
7/24
02.09.2021 - Cement pouring & finishing of foundation
8/24
Brick manufacturing
9/24
09.09.2021 - Wall construction ground floor
10/24
19.09.2021 - Cement mixing & wall construction ground floor
11/24
26.09.2021 - Ground floor wall construction completed & preparation for 1st floor
12/24
02.10.2021 - Mounting of struts prepared from recycled timber & floor preparation for 1st floor
13/24
13.11.2021 - 1st floor preparation
14/24
27.11.2021 - 1st floor preparation for cement pouring
Content from Vimeo can't be displayed due to your current cookie settings. To show this content, please click "Consent & Show" to confirm that necessary data will be transferred to Vimeo to enable this service. Further information can be found in our Privacy Policy. Changed your mind? You can revoke your consent at any time via your cookie settings.
15/24
30.11.2021 - 1st floor cement pouring
16/24
02.12.2021 - Cement pouring & finishing of 1st floor
17/24
18.12.2021 - Wall construction 1st floor
18/24
28.01.2022 - Interiour construction of experimentation tables
19/24
28.01.2022 - Interiour construction of experimentation tables
20/24
29.01.2022 - Construction of roof trusses with recycled timber
21/24
11.02.2021 - Mounting of roof panels & finishing of roof
22/24
02.04.2022 - Facades painting & mounting of window frames
23/24
25.04.2021 - Finishing of experimentation tables & test run of gas connection
24/24
06.06.2021 - Mounting of windows & finishing of laboratory block